Major Road Construction Projects

Suncrest Drive

Construction to repair Suncrest Drive will begin this week. Construction will take place on the downhill traffic side of the road first. This half of the road will be closed while one lane in each direction is maintained on the uphill half. Then the closure will flip sides. The project will take approximately 5-6 months and the entire road will be reconstructed.


Manilla Drive

A storm drain project is being installed on Manilla Dr. This will affect traffic in the area so please try to avoid the area.

13800 South Construction Update


Draper City has completed the installation of a storm drain pipe under the canal on 13800 South (just east of 300 East). The work to extend the storm drain from the canal to 300 East will start in early to mid-April and will be completed mid- to late May. More information regarding potential traffic delays in this area will be provided when it becomes available.
Water Pro is currently installing a new water line in 13800 South from approximately 300 East to Bangerter Pkwy. This project should be completed by April 7th. Minor traffic delays are expected through Water Pro’s construction area, as they will keep one lane in each direction open to the public.
The intersection of 13800 South and Bangerter Parkway will be widened this summer to provide additional traffic lanes in all directions. Construction is anticipated to begin in June and be completed by October. More information will be provided on this project when it becomes available.
For more information on these projects, call Todd Hammond at (801) 576-6336.
IMG_5956

Bangerter 600 west header 2

600 West Update - April 20, 2017

LEFT TURN DETOUR ON 200 WEST


The left turn detour started today for eastbound Bangerter to northbound 200 West. Drivers wanting to make a left hand turn at 200 west will be detoured via 600 West and 13800 South. This detour will last approximately two weeks and will allow crews room to work on mainline Bangerter. This intersection will become a right-in-right-out after the new 600 West interchange is complete. Please see map below.

New traffic pattern 3 30 17 New traffic pattern 3 30 17

200 West detour



PROJECT COMPLETION

We are nearing project completion and anticipate wrapping up by the end of May. Thank you for your patience during the project. Please let us know if you have any questions.

Upcoming Work

Constructing on and off-ramps
Landscaping
Installation of median at 200 West intersection
Removal of traffic signals at 200 West intersection

Ongoing Work

Pouring concrete on 600 West
Asphalt paving on 13490 South
Constructing curb and gutter on ramps
Signal work on 600 West interchange
Installation of roadside barrier and fencing


Lane Changes on Bangerter

All lanes will be open during peak travel times
6 am to 9 am - Monday to Friday - eastbound
4 pm to 7 pm - Monday to Friday - westbound
12 pm to 4 pm - Saturday - eastbound and westbound (excluding some weekends as noted) Lanes will be reduced by 1 or 2 lanes in each direction during off-peak travel times.


IMG 8814

Crews pouring concrete on the eastbound off-ramp


Project Details

A grade separated interchange will be installed at 600 West. Bangerter Highway will be raised approximately 12 feet to cross over 600 West.
Right turns will still be accessible at 200 West
The new interchange will tie in to local roads on the north and south sides of Bangerter to improve access to local destinations



What to Expect during construction

Traffic and pedestrian detours
Noise
Vibrations
Dust
Business access will be maintained

Work Hours

Crews will be working 24 hours a day, 7 days a week


IMG 8807

Crews work on 600 West, south of mainline Bangerter



Questions or Comments

Please let us know if you have any questions or comments.
Thanks!

600 West Interchange Team
801-649-5476
bangerter600west@utah.gov
udot.utah.gov/bangerter600west