Major Road Construction Projects

Detour Map of summer road construction projects

Suncrest Drive


Work is underway to reconstruct 3.2 miles of Suncrest Drive from Traverse Ridge Rd. to the Draper City limits. This project should be completed by the middle to end of October.

Two lanes of traffic will be open throughout the duration of the project. Traffic delays should be minimal. The speed limit has been reduced to 30 mph through the construction area and biking is prohibited through the construction zone.

Bangerter Parkway and 13800 South Intersection


This project is nearly completed and all traffic lanes are now open.  Landscaping and other finish items on this project will be completed by the end of October.

The Utah Department of Transportation (UDOT) is working in conjunction with Draper City to improve the intersection at 13800 South and Bangerter Highway.  This project will provide an additional through lane for the north, west, and south legs of the intersection, as well as an additional left-turn lane on each of the north and west legs to improve mobility and travel times. Each leg will maintain one right-turn lane, and a raised median will be installed in the west leg to improve safety.  


13200 South - Boulter to Highland

 
When completed, this project will connect 13200 South from Boulter Street to Highland Drive and curb, gutter, sidewalk and a complete new roadway will be constructed.

Connecting this road will add an additional east-west connection to the east side of the City.  This will reduce the congestion currently being experienced at the 1300 East and Pioneer Road round-a-bout and the 1300 East and Highland Drive intersection.  It will provide a more direct route for east side residents to the two schools located on 1300 East and 13200 South.  The addition of sidewalks will also make pedestrian access much safer.

The project is nearing completion and the roadway should be opened to the public by October 7th.  Landscaping and other finish items on this project will be completed by the middle of November.


Pioneer Road


Pioneer Road from 600 East to 700 East  will be widened and curb, gutter and sidewalk will be added in these areas. The asphalt pavement in these areas has deteriorated and will be replaced.  The addition of curb, gutter and sidewalk will improve storm water collection and provide for safer pedestrian movement.  

The road is scheduled to be completed and re-opened by October 2nd.  Landscaping and other finish items on this project will be completed by the middle of November.

Construction Update:  Bangerter Highway & 13800 South     

Date:  Sept. 8, 2017

Current Activities

Crews are currently raising utility manholes and prepping for light pole installation. This work will continue through the middle of next week.

Upcoming Activities

ADA ramps, landscape restoration, light pole installation, signage work and lane messaging will take place next week.

Lane Shifts

For the duration of the project, construction barrels will remain in place on all four legs of the intersection to help guide traffic through the work zone. Drivers should exercise caution, as lanes are narrow.

Be aware of changing pedestrian conditions in the work zone. Please adhere to sidewalk closures and use designated alternate routes as indicated.

What to Expect

  • Construction Activities Monday - Friday, 7 a.m. to 5 p.m.
  • Lane closures and width restrictions
  • Sidewalk closures and pedestrian detours
  • Temporary access restrictions
  • Increased dust, noise, and vibration during work hours
  • Construction vehicles entering and exiting the roadway

Plan Ahead

 To avoid delays during construction, drivers are encouraged to use alternate routes as available. Visit udottraffic.utah.gov for real-time traffic information